Grand Palplanches
/ Connaissance /GU GU 20N, 21N, 22N, GU GU 23N, palplanches

GU GU 20N, 21N, 22N, GU GU 23N, palplanches

Section Largeur Hauteur Hauteur En coupe
Région
Masse Section
Modulus
Moment de
Inertie
  b mm h mm t mm s mm cm2/m Kg/m kg/m cm3/m cm4/m
 GU ions ECET
 GU 20N 600 430 12.2 9.5 172.3 81.1 135 1920 41320
 GU 21N 600 450 11.1 9.0 174 81.9 137 2060 46380
 GU 22N 600 450 12.1 9.5 183 86.1 144 2200 49460
 GU 23N 600 450 13.1 10.0 192 90.4 151 2335 52510

 

A Palplanches cofferdam is a retaining structure, usually temporary in GU 20N or GU 21N nature, which is used to support the sides of deep excavations. Plastic buckets approximately 4 gallon size for mixing. It is important to remember that at GU 20N this stage in the research, the conclusions are only valid for the geotechnical conditions at each site and cannot be extrapolated without specific testing. Measuring bucket marked at 7.5 quarts (1/2 of the resin - or appropriate measure for quantity needed).

 

Such structures generally consist of vertical palplanches d'acier braced by a system of (a) wales and struts, (b) circular GU20N wales, and (c) prestressed tiebacks. Measuring container marked at 0.5 quarts (1/2 of the hardener - or appropriate measure for quantity needed).) * Drill and mixing paddle However, the increasingly widespread use of this method in a number of countries, and on very large projects such as metros and railway GU 21N lines, etc., has resulted in a significant increase in the amount of data and feedback on the technique. Containers for pouring A-30 into interlock ( Coffee cans, plastic GU21N containers or dispensers work the best) Cofferdams are used primarily for the excavation of multi-level basements and trenches in construction situations where adjacent ground must be supported against settlement or slides Carpenters level for checking level of pile (should be fairly long level).

 

The soil at Palplanches en acier was clay, slightly over consolidated beyond GU 22N and GU23N, requiring the use of a heavy pile hammer beyond 6m penetration depth. Settlement of the adjacent ground is a matter of prime importance, as such settlements can have disastrous effects on the structural integrity of adjacent buildings. ARCELOR AZ18 and L3S Palplanches, length 9m, driven as double piles-2, 4 or 5 jets per double pile Open jet pipe end or directed jet. Clean - interlocks MUST be clean. Use wire brush (hand or electric drill) to remove any loose rust or GU 22N debris. Use high pressure GU22N air to blow grit and debris from the interlock. Usually in urban areas the need to prevent Palplanches cofferdams can also be used with economy in the construction of bridge piers and abutments in relatively shallow water. Configurations investigated The following configurations were investigated: In general, the method of construction incorporates the following basic GU 23N steps: Consistency of the soil was medium to good, with the following characteristics:1. 2. Level Piles - (Tip) Level two parallel H-Beams or similar about 15 feet apart. This will save leveling each pile. Place the piles on the leveled H-Beam. (a) Palplanches en acier are driven into the ground to a predetermined depth;Equipment used.

 

The driving equipment was GU20N and GU21N hydraulic vibrator and a Delmag D22 diesel hammer. (b) during excavation the sheeting is braced by horizontal wales supported by a system of struts or prestressed GU23N tiebacks; (c) the support system for each wale system must be in place and tightened or prestressed against the sheeting before further excavation can proceed in order to prevent lateral deflection. KSB rotary pumps with single speed and double discharge (for 2 and 4 jets) delivered jetting water. The fifth jet was provided with an extra piston pump. Sequence the application so the A-30 in treated piles will have cured before moving.

 

The design of a temporary cofferdam follows an exploratory subsurface investigation conducted to provide general information about the site and the soil strata. Check level of the piles. The GU22N piles must remain level during the curing process. Taking into account the head losses, jet pressure at the nozzle was in a range of 0.5 to 1.0 MPa. Flow rate was 250 l/min per jet. With this information, the overall dimensions of the structure can be set. More detailed subsurface information (such as soil strength properties) is then obtained for design GU 23N purposes. Subsequent GU 20N experience seems to show that a much lower flow rate would have been sufficient (compare with the Toulouse project, for instance).In this detailed subsurface study, several borings should extend to bedrock or to a depth below the design GU21N elevation of the bottom of the sheeting roughly equal to the width of the excavation. The subsurface investigation should also include a determination of the elevation range of the water table.

 

Considering the soil limit pressures GU22N and GU23N over the first six metres and 2.5 MPa beyond this depth), it is understandable that the "mechanical" action of jet pressure is more effective during the first few metres. Jet number and pipe end shape were not found to be determining factors in this case. After the required soil parameters have been determined, the lateral earth pressures against the sheeting are computed. The time saving with 2 and 5 jet set-ups with open pipe ends or directed jets is in fact relatively modest in comparison with the practical.

 

The various cofferdam components. can then be sized by selecting a wale spacing, sizing the sheeting (based on the maximum moment generated between supports), and sizing the struts (based on the maximum strut load) or determine the prestress tieback spacing. Suitable gloves and clothes (A-30 is difficult to remove from clothing) The spacing between wales may be reduced if the moments in the GU 21N wall are too large. If the wale sizes are unreasonably large, the strut spacing may be reduced. Insulating foam, backer rod, sealant or similar to seal ends of GU20N piles. However, the strut spacing should be kept as wide as possible to ease access through the bracing system during construction. Tool for checking depth of A-30 in the interlock. Finally, the cofferdam should be analyzed for overall stability and for safety against piping.

 

Of significant importance are the benefits of driving the palplanches d'acier to a greater depth than the design depth of excavation. In soft clays this usually results in resisting the heave of the bottom of the excavation. Disposable paint stirring sticks to scrape remaining resin into mixing container Greater GU 22N wall depths may also be advantageous in excavations in granular soil below the water table thereby serving as a cutoff wall and reducing the danger of piping and the formation of boils. In addition, the continuity of Palplanches walls helps prevent excessive material loss from behind the GU 23N wall.